Pile optimization. High density residential complex. 2021.
NDA protected location
Goals & Problems
  • Existing geosurvey limited us by bearing capacity of piles
  • We decide to discover true bearing capacity of piles
Plan & Realisation
  • Developer agreed to invest small amount of funds into extra geosurvey
  • 3 month and $30k was spent
  • Every approvement by goverment was granted in that time span
Result
  • For $30k spent the comulative result in mid term was $850k of economy
  • Long term cost reduction effect was $2,7M